|
|
|
The first call to this address
was to investigate a boiler overheat problem.
The
boiler – an Ideal W2000 wall hung had been installed for 19 years. I
tested the thermostat and it worked correctly. I tested the pump which was also
working correctly. With any pump or thermostat fault eliminated the
symptoms suggested that the heat exchanger was blocked with sludge and residue. Talking to the owner further revealed that some of the radiators were intermittent and/or cold at the bottom, hot at the top - a classic sign of residue blockage. Remedy I
discussed options with the owner and submitted a quote for boiler replacement,
new controls powerflush, new
feed/expansion tank, and TRV’s to all rooms except bathrooms. The quote was
accepted. The
installation took 3 days :- Day
1 - De-commision Ideal W2000 Boiler
and Powerflush the System Day
2 - Fit TRVs and replace Rad
Valves. F/Exp Cistern Day 3 - Install new boiler and flue and commission. Method
Statement A
Let-by test and tightness test were satisfactory. The gas supply to the existing
boiler was isolated and capped off. The system was drained down and the old
boiler disconnected and removed.
Once
removed the heat exchanger casing was split open and the excessive build up of
debris could clearly be seen inside. See
Pic The
system was then powerflushed and the TRVs and Radiator Valves were fitted. The
position of the new boiler was determined by use of the template provided by the
manufacturer. The flue was to go through the same opening as the old boiler’s
balanced flue and then bricked around. The
template was used to plot the holes for the boiler mounting plate, which was
then fixed to the wall. The new boiler was then hung from the mounting plate. The
gas supply pipe was modified to feed the new boiler.
The
condensate pipe was then fitted which ran into an existing washing machine waste
pipe. The
flow and return pipes were then connected. The
flue was then cut to size and fitted. The
system was then re-filled and vented. The
gas supply was tightness tested and found satisfactory. The
boiler electrics were connected, the old boiler’s switched live was used and a
new permanent live was taken from the existing double pole switch. A
new room thermostat and 7-day programmer were fitted. The
boiler was then fired up and commissioning checks were made. The
flue pipe penetration was the bricked up and made good.
|